Northeastern South Carolina

To meet the needs of transporting large volumes of raw materials from a nearby quarry, this new mining operation required significant capacity for loading out rail cars for transportation to various processing facilities across the US.  This long-neglected brownfield site formerly served by CSX was selected and developed to loadout as many as 20 rail cars per day.  

CivilSmith worked closely with the industry to develop initial track layout concepts and ultimately developed detailed track plans that were reviewed and approved by CSX’s Design & Construction department.  CivilSmith worked closely with the industry’s engineering team to develop plans that included a unique layout for efficient use of limited trackage for both the industry’s loading operation as well as CSX’s operation for quick setoff/pickup operations along this mainline corridor.

CivilSmith provided track construction specifications, assisted with the bidding process, and provided valuable track construction phase services to include material inspections, responses to RFIs, and construction observation visits with detailed reports.

Interactive Aerial Imagery (Google Earth)
Project Photo Gallery
Construction Phase

Brownfield Site at Mainline Connection

Construction Phase

Brownfield Site Before Construction

Construction Phase

Completed CSX Mainline Turnout

Construction Phase

NARSTCO Steel Tie Turnout

Construction Phase

Tracks Completed by Bundrick Rail Services

Construction Phase

20-Car Capacity Both Tracks

Construction Phase

NARSTCO Steel Tie Track Construction

Construction Phase

Tail End of Loadout Operation

Construction Phase

NARSTCO Steel Turnout Set

Construction Phase

End of Tail Track

Construction Phase

Tracks in Service and Ready for Use

Construction Phase

Loadout Operation